Client project: Province of North Brabant
Management: Province of North Brabant
Client: Ippel Nieuwendijk B.V.
De Gantel is a watercourse that runs to the east of the village Nieuwendijk.
The work consists of the design, manufacture, installation, rental and removal of a temporary road bridge (bypass) during the renewal of the bridge over De Gantel near the N214 in Nieuwendijk. The bridge is provided with an epoxy layer, sprinkled with hard stone to get sufficient grip on the elements for traffic. For the construction of the bridge (DVA 9000®) bulkheads were used that can carry a traffic class VK600. The entire project was carried out under our own management. 
Assembly time: 3 days (including pile-driving sheet piles underneath the abutment)
Disassembly: 2 days